US 160 - Alamosa East

Project Owner CDOT
CDOT Region 5
County Alamosa
Description of Work Resurfaces six miles of US 160 in asphalt.
Estimated Total Project Cost $3,758,589
ARRA Funds $3,683,041
Project Status Construction Complete
Start Date July 2009
Completion Date September 2009
Percentage Spent 100%
Contractor Elam Construction Co.